South Siesta Key Beach Restoration Project, Phase II  (2015)

Humiston & Moore Engineers designed and permitted the South Siesta Key Beach Restoration Project, Phase II. The project include dredging approximately 690,000 cubic yards of sand from offshore borrow areas  using a hopper dredge and placing sand on the beach and in nearshore area. This project is the first maintenance following the 2007 beach fill project. Construction is to start in March 2016.

 

Project Construction Updates

 

 

Pre-construction: January 2016 (Click on Photo to expand)

Construction:

2014-03-04

Construction: March 2016 (Click on Photo to expand)

Post-Construction: May 2016 (Click on Photo to expand)